FRONTLINE SERVICE: ISSUANCE OF BUILDING PERMIT (CONSTRUCTION PERMIT)
OFFICE OF THE MUNICIPAL ENGINEER
Municipal Hall, San Nicolas, Ilocos Norte
Head of Office: Venonie V. Coloma, C.E., Municipal Engineer
Contact Number: (077) 600-0884
ABOUT THE SERVICE: This service is offered in compliance with the rules and regulations set forth in PD 1096 otherwise known as the National Building Code of the Philippines.
If requirements are complete, this transaction can normally be completed in three (4) working days.
SCHEDULE OF AVAILABILITY OF SERVICE:
MONDAY – FRIDAY
8:00AM – 5:00 PM
HOW TO AVAIL OF THE SERVICE
STEP |
STEPS/PROCESS |
DURA-TION |
REQUIRE-MENTS / FORMS |
FEES |
PERSONS RESPON-SIBLE |
LOCATION |
|
CLIENT |
SERVICE PROVIDER |
||||||
1
|
Secures application forms and other requirements | Provides the client with a short briefing on the service and its requirements
Note: Applicant shall secure Locational Clearance prior submission of application to Office Building Official in accordance with Zoning procedure of MPDO
|
1 hr. | Building Permit Forms and Zoning Clearance Forms | None | Engr. Venonie Coloma/
Angelita Agonoy/ Caguiat/
|
Office of the Municipal Engineer / Office of the Municipal Planning Coordinator |
2 | Submits the accomplished application form and other documents
|
Receives and reviews application, auxiliary and other related permits as to completeness and correctness of related plans and supporting documents and advice applicants for any deficiencies observed. | 3 days
|
– 5 sets of building plans (blue print) & specifications and classification of the building signed and sealed as to structural,elctrical,sanitary,architectural,mechanical, electronic forms whichever ir is appropriate and documents plus clearances as applicable (Tax Declaration)/TCT, Certificate of Non-Delinquency,Deed of Sale, Contract of Lease, Brgy. Clearance, Cost Estimate and Special Power of Attorney, Construction Logbook | None | Engr. Venonie Coloma/
Edna Tolentino/ Mun. Fire Marshall/ Angelita Agonoy/ Caguiat/
|
Office of the Municipal Engineer / Office of the Municipal Planning Coordinator /
Bureau of Fire Protection Office
|
3 | Proceed to Pay fees
|
Site Inspection of the propose site
Assessment of Building Permit Fees
Issues Official Receipt |
4 hrs.
|
Building Permit Forms
|
As per prescribed fees based on National Building Code (PD 1036) and Local Tax Code | Engr. Venonie Coloma/Engr. Jarah Mae Ganal/
Edna Tolentino
|
Office of the Municipal Engineer / Office of the Municipal Planning Coordinator |
4
|
Proceeds to Engineering Office (show Zoning Clearance,Fire Clearance & Official Receipt)
|
Receives Documents for signature/
approval
Segregates record data and Issue approved building permit to the client |
3 hrs.
|
Building Permit Forms
|
None | Engr. Venonie Coloma/
Edna Tolentino/ Mun. Fire Marshall/
|
Office of the Municipal Engineer |